Monday, September 14, 2009

TVF&R Fire Station 58 Boulton

Project: TVF&R Fire Station 58 Boulton
Location: West Linn, Oregon
Architect: Peck Smiley Ettlin Architects
4412 SW Corbett
Portland, Oregon
97239
General Contractor: CSI Construction
Square footage: approx. 8,391 sq. ft.
Status: Completed Winter 2010

This was another fire station for Tualatin Valley Fire and Rescue in the West Linn area. The style of station 59 in the Willamette area was to match the buildings in the surrounding area. Station 58 on the other hand is located in a residential area and was not strict as station 59. Although the community was allowed input to the final design.

It was a 2-story structure and all wood construction. The second floor foot print is 9 feet smaller all around than the floor below. The walls for the second are supported on glulam beams which are then supported on columns down to the foundation. There is a beam line that runs north/south at the roof to support pre-manufactured press-plate trusses. The trusses were a mansard style and it created a well area for mechanical units to be placed and a solar panel on the roof. They also mounted a radio antena in this area. The east side the roof extended to the building edge below as to create a patio on the second floor.

Lateral forces from the roof diaphragm were taken out through shear walls on the second floor and transferred through drag struts and the second floor diaphragm. Beams/columns were sized to resist the lateral forces.

Most of the second floor framing used glulam beams. Over the apparatus bay steel wide flange beams were used which were supported on HSS columns to the foundation. The depth and cost of using glulam beams in this area got too deep and costly and they required as much clear height as possible to service the trucks and other equipment.

Because the project was built on a slight hill, extensive retaining walls were required to level the project site. A portion of the retaining wall system was not only designed for the soil pressure, but also the load from the trucks, as the drive way curved into the building. The construction took considerable time and in the end came out looking nice. A portion of them allowed for a planter near the street level.

Both this station and Station 59 replace existing stations. The capacity nearly doubled for Station 58 compared to the previous station.


In addition to Station 58 and 59, our office did Station 34 and Station 53 an several others.

Thursday, September 3, 2009

TVF&R Fire Station 59

Location: Willamette Falls/West Linn, Oregon
Architect: Peck Smiley Ettlin Architects
4412 SW Corbett
Portland, Oregon
97239
General Contractor: CSI Construction.
Square footage: approx. 7,013 sq. ft.
Status: Completion Fall 2009


The fire station is a 2-story all wood construction. The only exception is where wood beams were unable to adequately span with the required load and clearance requirements. Steel wide flange beams were used in these cases with wood nailers fastened to the top flange with carriage bolts. Open web wood joist were used to span over the apparatus bay and repeated in the roof at the same location to minimize additional loads to the second floor joist. The remainder of the floor and roof framing was accomplished by using plywood web joist.

The foot print of the second floor was smaller than the first floor, creating an offset above. A steel angle was bolted to the studs to carry the brick on the upper wall. Many of the windows around the building had curved lintels. Steel HSS jambs and HSS headers were used to acheive this.
The construction of this building went fairly smooth, with the usual twist and turns. Head clearance at the main stair became an issue and we had to modify the frame that was already in place. The stair at the back needed an additional support, so a rod was added and supported off the glulam beam above.

In addition to Station 58 and 59, our office did Station 34 and Station 53 an several others.